Under implementation

Sungun Copper Mine

geographical location:

The Sungun Copper Mine is located on the international metallurgical belt called Alp Himalaya in East Azarbaijan province, 105 kilometers northeast of Tabriz.

climate:

The cold and frosty winters and the mild summer are weather characteristics of this region.

Ajin Mining Company has been operating in the mine since 2000 and has so far completed more than 210 million tons of gravel and 32 million tons of minerals extracted.

Contract:

The new contract was dated 1/1/1/1, with the subject of drilling, blasting, dumping and mining of minerals for 5 years and amounting to 106,250,000 tons. With the announcement of the addendum No. 3, the contract has been extended to 22,500,000 tonnes for another year.

Lead and Zinc Anguran Mine

geographical location:

The Anguran mine is located 130 kilometers southwest of Zanjan and is bordered by the West Azarbaijan province.

climate:

The Anguran mine is located in the mountainous region with very hard winters and mild summers.

Ajin Mining company has been operating in this mine since 1388 and, given the valuable experiences of managers and experts, has managed the precise design of landslides, and now the mine is in safe condition. During this time, 130 million tons of gravel and 7 million tons of minerals were extracted.

Contract:

The new contract dated 92/7/12 has been concluded with the subject of the operation of grabbing and extraction of minerals for a period of three years, amounting to 54,630,000 tons, and extended by the notification of the extension until April 3, 1996.

Construction project of Gheshlagh Stage Reservoir Dam

geographical location

Gheshlagh Dam is located 15 km north of Sahneh and 60 km from Kermanshah.

Permanent term: 48 solar months

Gheshlag Reservoir Dam is being implemented with the aim of supplying urban water to the city of Sahneh, as well as the water needed for the agricultural land of Sahne Plain and Cham Khamal. The physical progress of the project is about 70% and the rial progress is about 98%.

This dam is of a pebble type with a clay core and 70 meters above the river bed.

The main project consists of excavating and embankment items of 3 million cubic meters, drilling and injection of consolidation and drainage of 35,000 meters long and about 40,000 cubic meters of concrete, with a reservoir capacity of about 50 million cubic meters.

The most important activities:

 

Activity description

Unit

Done year 94

The cumulative amount is done

 Excavation and excavation

Cubic meter

           25,754     1,139,544
 Run Rockfall Dam

Cubic meter

         194,711         485,235
 Clay core and strainer

Cubic meter

         101,439         191,252
 Implement the body filter

Cubic meter

           29,633           43,454
 Run the A-Zone river shell

Cubic meter

           68,133         111,154
 Rip rap and rock protector

Cubic meter

             8,706           20,122
 Underground digging

Cubic meter

                    –             7,000
Meshing

Kilograms

                    –             3,200
Shuttercrime

Sq. M

                    –             7,700
 Drilling and injection

Meters long

             8,605           69,805
Steelwork

Kilograms

           30,951         369,255
Formatting

Sq. M

             1,158             9,532
Preparation of concrete and structural concrete

Cubic meter

                 401           19,618
 Preparation of concrete and filling materials

Cubic meter

                 637           12,276
Preparing, Bending, Cutting and Threading Fittings

Ton

                    –             1,200